A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling - Illustrated with a case study
Zhang, L. Q.; Yue, Z. Q.; Yang, Z. F.; Qi, J. X.; Liu, F. C.
刊名TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY
2006-11-01
卷号21期号:6页码:636-649
关键词back-analysis displacements modulus in situ stresses 3-D FEPT field tests
ISSN号0886-7798
DOI10.1016/j.tust.2005.12.001
文献子类Article
英文摘要This paper presents a displacement based back-analysis method for the determination of rock mass modulus (E) and the horizontal in situ stress (P) perpendicular to the axis line of the tunnel excavation in hard and intact rock masses. The rock mass is assumed to respond in an isotropic and linear elastic manner. Essentially, the method is a best-fit solution of back-analysis by comparing the measured displacements near a tunnel face during excavation with those calculated using a three-dimensional finite element method. The method can be applied efficiently and effectively by iterative algorithms such as direct search technique and damping least square technique. In particular, a three-dimensional finite element pattern technique (3-D FEPT) is used to compute the theoretical displacements for saving computation time. The method is further illustrated with a case study. The case study deals with a test adit at Zhanghewan Pumped Storage Power Station in Hebei Province, North China. It is shown that the back-analyzed results of E and P are reliable and representative for the actual rock masses. (c) 2005 Elsevier Ltd. All rights reserved.
WOS研究方向Construction & Building Technology ; Engineering
语种英语
出版者PERGAMON-ELSEVIER SCIENCE LTD
WOS记录号WOS:000238867700006
内容类型期刊论文
源URL[http://ir.iggcas.ac.cn/handle/132A11/66364]  
专题中国科学院地质与地球物理研究所
通讯作者Zhang, L. Q.
作者单位1.Chinese Acad Sci, Inst Geol & Geophys, Beijing 100029, Peoples R China
2.Univ Hong Kong, Dept Civil Engn, Hong Kong, Hong Kong, Peoples R China
3.Beijing Hydroelect Invest & Design Inst, Beijing, Peoples R China
推荐引用方式
GB/T 7714
Zhang, L. Q.,Yue, Z. Q.,Yang, Z. F.,et al. A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling - Illustrated with a case study[J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY,2006,21(6):636-649.
APA Zhang, L. Q.,Yue, Z. Q.,Yang, Z. F.,Qi, J. X.,&Liu, F. C..(2006).A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling - Illustrated with a case study.TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY,21(6),636-649.
MLA Zhang, L. Q.,et al."A displacement-based back-analysis method for rock mass modulus and horizontal in situ stress in tunneling - Illustrated with a case study".TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY 21.6(2006):636-649.
个性服务